Thursday, April 25, 2013

Is winter over??


The extended winter of 2012-2013 seems to be abating this week. Good riddance...and let's be thankful we aren't located in Minnesota where Superintendents don't anticipate opening some golf courses for three more weeks!! Talk about a short season!!

We have had a busy spring. To date we have completed wall to wall application of pre-emergent crabgrass herbicide, spot fertilized thin areas of rough, repaired and sodded the bunker on 16, fine graded and seeded the berm project and the 6 bunker removal areas, started up irrigation, and ground up and filled many tree stump holes! We have also been cleaning a very messy golf course from winter's winds and snows...with thanks for many members' efforts on March 23rd.

The golf course is making slow progress as of today. We are beginning to transition from clean up tasks to everyday maintenance tasks for golf. We also plan on working on a few projects during the next few weeks. These include bunker edging and improving, sprinkler head edging, broadleaf weed control, hyperoides weevil control and seeding thin areas of rough.

BERM PROJECT SUCCESS

The berm project completed last December has helped to solve the poor drainage and unsightly area right of the 17th fairway. This area had been ugly for years and once grass germinates later in spring the improvement will look much better! However the picture isn't complete unless we look at increased water holding in irrigation ponds. The project was designed to help us become less reliant on water purchases from the city of Warwick by allowing us to store more water. Our ponds are holding an extra 700,000 gallons (12-14" increased water level) painting an even better picture of Berm Project success!!

CLUBHOUSE LANDSCAPE IMPROVEMENTS

Since January, a subcommittee of the Greens Committee has met weekly to plan improvements to our clubhouse and golf course plantings. (Mary Bagley, Mark Marcantonio, Rosemary Pariseault and Patrick Gertner) We have surveyed all beds on the golf course, evaluated each bed's needs, defined functions of each area, defined priorities and irrigation capabilities bed by bed, and weighed member expectations to help us plan facility wide improvements. We are working with a prominent Rhode Island landscaper (Dave Renzi of Out In Front Horticulture) who has broad plant knowledge to help us create planting themes that will be present throughout the property. We expect plans will take a few years to complete but believe plantings this spring will make immediate impact.

Plans for spring 2013 include improving the front of the clubhouse, the bed behind the 16th green and 17th tee beds. We will begin by preparing beds for planting a few weeks later. Our aim is to proceed slowly adding plants so beds aren't simply stuffed with plant material. Small plants will be added and will be spaced to allow for their maturity. Each bed will be a work in progress as the Committee will re-evaluate each bed....we reserve the right to make changes after the changes!! Stay tuned as we will report our progress and plans in future emails.

Tidbits....Greens height of cut will be lowered again Friday morning....Intermediate rough was being double mowed yesterday when a hydraulic lift arm failed. If the part arrives Friday, we will complete intermediate rough mowing by Saturday am....The small greens sprayer is also waiting for parts; thankfully we have two sprayers....13 fairway is growing at twice the rate of others because of the many fertilizers applied last fall to hasten growth....Paving contractor has been delayed for a week or two more....Tree Improvement Committee has asked us to grow up rough on the left side of #2 to better challenge par for drives long and left.....Greens aeration is scheduled for the week of May 6. This will not be a full blown aeration process; we will only punch holes with solid tines and is much less disruptive to greens and golfers than the September process....Please thank our wonderful crew for all their spring efforts; best crew ever!!

Patrick M Gertner CGCS

Wednesday, April 3, 2013

April 3, 2013

Thanks again to members who helped us clean the golf course on March 23rd. Thanks to you, our clean up efforts are progressing quickly despite the heavy workload caused by windy winter storms. Much remains, however and we will continue until complete!  

Turf came out of winter in great shape. We are still waiting (like you) for warmer temperatures for growth and initial green up during a very cold and windy spring.  By Saturday April 6th we plan on applying both a wetting agent to greens (to aid soil water retention) as well as early spring growth regulator that will speed greens up and prevent the emergence of Poa annua seedheads during May and June. We will need a non windy day however.... 

We have begun to fill our irrigation pond at 18 using our well located in the driving range. We are already storing more water than we've been capable during past years because of the pond extension/berm project. We will repair winter erosion on the edges and reestablish turf as quickly as possible.  

Irrigation system has been turned on and is ready for the season! As of April 3rd last year, we had already pumped over a million gallons of irrigation water. As of today in 2013, only 10,000.

Thanks for everyone's patience as we ready and improve your golf course for the season. We have all hands on deck cleaning the golf course as quickly as we can!

Tidbits.....Greens were opened March 14....Cartpath construction begins this month...O/B and hazard stakes, and bunker rakes will go out by Friday....We will get bunkers cleaned and raked next week....A tree trimming crew will be here next week to remove damaged maple at 9 Tee/10 Green, and a few other storm damaged trees....Stump grinding and filling will continue through April...Laser reflectors that are missing have been ordered...Pre-emergent crabgrass control begins next week in roughs....

Tuesday, March 5, 2013

WINTER UPDATE


It's early March!! We are nearing the end of a New England winter complete with cold, storms to remember (or forget) and almost hurricane force winds! Unfortunately, winter isn't done as more cold and snow are forecast for later this week and beyond. However, I'd like to report on your golf course as of today.

Winter 2013 has been a very nice winter for turf. Ice formation that prevents soils from breathing is always our primary concern regarding turfgrass health and and as of today we have none. Additionally, there isn't enough winter left for new ice to form and cause damage. We are also clean of snow mold diseases today and we are confident turf will remain free of disease when golf begins later this month.

Storms have damaged a few trees on the golf course but overall damage is not severe. Cedar trees and pines have taken the largest hit from heavy snow immediately followed by severe winds. Most injured trees have been pruned from ground level and clean up and chipping will happen into later March. (Since we don't own a tree chipper, we save all that work for the week we borrow one.) The most important tree that damaged is the large cedar on the left side of #2, along the slight dogleg curve of the hole. The tree is still standing but she isn't pretty.

The unused scoreboard located at the practice green was also a storm casualty as numerous cedar trees fell onto it. It has been removed.

During winter we have removed dead pines along #3, #10 and at the 16th tee. Other trees have been removed to improve the health of turfgrass, especially along #13 to add much needed sunlight penetration and air movement for the fairway. A few trees have been removed on #5 in anticipation of the cartpath paving project that will be done this year.

We are planning a member golf course clean up day for Saturday, March 23rd. More information as plans develop.

See everyone very soon for much needed outdoor recreation!







Wednesday, November 21, 2012

Brief Look At The Future

2013 Golf Course Outlook

Plans for 2013 are underway and I'd like to update you the ideas we are working on to improve your golf course. We are constantly driven to learn new and utilize technology and ideas from turfgrass researchers and successful Superintendents across the world to improve your golf experience. (Not all ideas are set in stone...but most are!!)

GREENS

Greens are in their best condition since I arrived to Potowomut in 2005, and should be wonderful to begin 2013 barring potential winter issues. (Greens will be sprayed to prevent snow mold diseases during the week of Nov 26) Through persistence and research, we have learned how to control our devastating nematode population moving forward. Partly because of successful nematode control during 2012, greens performed very well during a stressful summer.

For 2013, we plan on introducing a program to provide "hormone therapy" to make greens stronger and healthier. Through natural seaweed based materials, our goal will be to fool the greens to speed or slow growth rates, and to manufacture roots throughout the growing season instead of the traditional spring and fall months. (Plant hormones are usually induced only by seasonal environmental changes but this program tells plants to behave differently than what the weather tells them.) Stronger root systems always correlates to higher quality turfgrass. Hormones will also be used to slow grass growth for increased green speeds.

COLLARS

Collars will be improved during 2013. Here are ideas we are planning:

1. Aluminum rear drive rollers on each greensmower will be sanded perfectly smooth this winter. The thought here is that after years of use rollers have become scratched and scuffed. It is quite possible these slight imperfections injure plants on collars while mowers turn on green collars during daily mowing.
2. Thinking of #1 above, greensmowers will be moved and stored in the shop on thick rubber matting that will prevent future scuffing of the drive roller from sand and soil particles in the shop. Crew members will load and drop off the mowers only from the rubber mat.
3. Many clubs with collars issues institute different turning regimens for greensmowers (the likely culprit of collar damage.) We plan on providing
mower operators pieces of plywood to place on the green collar that they will make their turns on. This way, the mowers will make their turn on top of plywood while turfgrass is never touched. This method has obvious labor costs to constantly move the pieces, but we feel the investment in the health of greens' collars is most important. This change would probably only be utilized during the stressful months of June through August.

FAIRWAYS

Bye bye Gray Leaf Spot (GLS). It wasn't nice knowing you.

Because of two infestations in two years, we have no choice but to apply fungicides to fairways and rough to prevent GLS. We can hope and wish for cold and harsh winter weather to kill disease spores that may be still present, but we will spray next summer regardless of how harsh our winter is.

Thirteen fairway is slower to recover from its GLS, but warm May and June weather will help to complete the task. (13 was seeded again with creeping bentgrass this morning (11/21) and was topdressed with leftover greens topdressing sand to protect new plants from winter weather extremes.)

All fairways were aerated by a contractor on November 12-14. (A few areas were aerated twice) Since fairways have demonstrated weakness the last few years, aeration is the best method to improving their health. This fall aeration process is again planned for 2013.

Soil casts from earthworms were present on fairways during wet spring and fall months. Although there is NO legal method to control earthworms in turfgrass, some Superintendents have observed that certain fungicide applications applied to combat northern turf diseases can reduce earthworm populations. We plan on learning more about these ideas during winter.

Thanks for a wonderful season during 2012! Have a wonderful Thanksgiving and come enjoy the golf course this weekend if you can as the current December forecast doesn't look great for golf!

Patrick Gertner CGCS



Monday, November 12, 2012

Fairway Aeration

Apologies to today's (Monday's) golfers who came to the club today and were surprised about fairway aeration that we began today. As many of you know, I was in Florence Italy until Sunday night and dropped the ball about notifying members of this important process. I will repeat, this time in Italian....Così spiacente!

It will take our contractor two days to complete fairways and intermediate rough. They are using three machines to complete the operation far quicker than we ever could. Fairways will be aerated at the closest spacing possible, and thirteen fairway will be aerated twice.

Aeration is an important process that provides many turf benefits:

1. Aeration helps to remove the 1" thatch layer that is made up of old plant
stems and plant parts that resist decomposition.
2. Aeration provides channels for rainfall, irrigation and oxygen into soil.
3. Breaking up the aerated soil cores provides a fine topdressing layer of soil
that helps keep the thatch layer in check.
4. Aeration will help push root systems deeper into soil.
5. Aeration will help fairways survive the heat of summer.
6. Since disease and insects thrive in the thatch layer, aerated fairways are
less prone to damage from these pests...including Gray Leaf Spot.

In addition to this process, we plan on aerating all fairways with a solid steel tine that brings up no soil before next May. Between these two processes and a chemical program to fight against gray leaf spot, we expect highly improved fairways for 2013 and beyond.

To our Monday golfers we sincerely apologize for beginning the aeration process without notifying you before your arrival. Thanks for your understanding!!

Patrick Gertner CGCS










Thursday, November 1, 2012

Hurricane Sandy

Hurricane Sandy roared through Potowomut on Monday but damage was minimal. Beside from the billion or so leaves left in her wake, only one significant tree was damaged, a maple located left of 10 green. Unfortunately, half of this tree fell on the ninth tee which sustained minor damage. The tee will be repaired by our crew soon. The "other half" of this silver maple will be removed because the remaining tree's weight now leans precariously to one side.

Our hard working staff has worked to clean away storm debris since Tuesday morning. Where leaves, sticks and branches littered 100% of the golf course then, we are now working quickly to return to pre-Sandy condition. Numerous leaf piles have been created by our crew and these will be picked up as soon as possible. Sticks and branches that are being taken off the golf course are being stored in our parking area and will be chipped up at a later date.

Overall, we are very lucky here at the golf course. We know of many friends, family and neighbors who are truly suffering in Sandy's wake. Our thoughts and prayers go out to them during this difficult time.

We hope to see you on the golf course soon.

Wednesday, October 3, 2012

Progress Report


Nice fall weather has allowed us to make significant progress these last few days.

GREENS

Greens have healed nicely after our mid September aeration. Height of cut has been lowered twice since their first mowing and are now within .005" (five thousandths of an inch) of the height they were mowed at all summer. They will be lowered one more time. With cooler weather of October, root systems will expand into the soil profile to prepare for next summer's stressful weather.

Sodding and plugging operations are nearly complete on greens. We worked on green collars this week and expect to complete them sometime next week. All sod used comes from our turf nursery by 2 tee. We will continually topdress sodded areas with sand to eliminate uneven surfaces caused by new sod.

Smaller areas not large enough to sod will be seeded to bentgrass.

TEES

Because we have focused on greens' improvement programs, tee aeration still remains but will be completed by October 15. Thin tees will be seeded.

FAIRWAYS

Fairways continue to improve and fill in. We have planted 1200 lbs of bentgrass seed to fairways and new plants are appearing. Plants are extremely small but can be seen in fairway bad spots. The goal is to add many new (GLS resistant) bentgrass plants to fairways through October 15 when the seeding operation will be halted. New plants will mature and fill in next spring giving us fairway turfgrass more resistant to GLS.

To push growth, fairways will be fertilized again tomorrow (Thursday)


Close up photo shows both small bentgrass plants after germinating as well as extremely small bentgrass seed that was broadcast today on 13 fairway. To initiate seed contact with soil, this turf area will be spiked in three directions Thursday to drive seed into soil. Aggressive establishment of GLS resistant turfgrass can only improve fairways over time.


Dr. Nathaniel Mitkowski, Turf Pathologist from the University of Rhode Island visited us last Wednesday to help us with out Grey Leaf Spot (GLS) issue. We will summarize points from his visit.

-He has seen plenty of GLS this year, even though he says its appearance in New England is rare. When GLS spores do arrive in New England, they usually arrive from the south with a specific hurricane. He said 2012's Hurricane Isaac did not bring GLS to New England because of its path to Rhode Island from the midwest. He did remind us of last year's Hurricane Irene with its southern path to Potowomut.

-Because of the warm winter of 2011-2012, he said spores from last year's GLS appearance at Potowomut (from Hurricane Irene) were never killed. He said it was likely that GLS became active at Potowomut during our very first hot weather in June. In other words, without a specific fungicide treatment to prevent GLS way back in late May or early June, our fairways were poised to be attacked by GLS again in 2012. GLS is a rare disease, its surviving through the winter to cause damage the next year even rarer still.

-At least two summer fungicide applications to prevent GLS are recommended (and are planned for 2013 and beyond.) He agreed with our aggressive seeding of bentgrass seed as the best long term course of action combined with chemical prevention. He also suggested a more aggressive fairway aeration program which is being pursued.

ROUGHS

Over 500 lbs of seed has been planted re-establish roughs afflicted by GLS. We will continue on this project until mid October. GLS prone ryegrass will no longer be planted in the rough as we will be using fine leaf fescues, tall fescues and Kentucky bluegrass. Ryegrass is a bad word around these parts from this point forward!

To push recovery and force growth, roughs will be fertilized in early October, six weeks early. This process will be repeated again in December or in spring 2013 if thin roughs remain.

ROUGH FIRST CUT

The first cut of rough's bad spots will be seeded before October 15 using the same rough seed mixture noted above.

Thanks as always for everyone's patience and kind words.

Patrick Gertner CGCS